Implementation

EXPECTED RESULTS
- Improved quality of the water environment and recreational potential at cascade of reservoirs in municipal "Arturówek" forest,
- Implementation of ecohydrological methods to sustainable water management in urban areas,
- Dissemination of ecohydrological methods among the decision makers and society,
- Elaboration of the scientific and applied background for the rehabilitation of key water systems in Łódź City as a instrument for implementation of Water Framework Directive EC
| Activity No | Activity Title | Realization Time (quarter/year) |
| A2.1 | Identification of design companies for the realization of planned investments |
I/2011 – I/2011 |
| A2.2 | Development of investment projects | I/2011 – IV/2011 |
| A2.3 | Realization of investments: Ecohydrological adaptation of the existing water reservoirs Bzura 7 nad Bzura 8 located above the „Arturówek” reservoir; exploitation of the reservoirs |
II/2011 – IV/2011 |
| A2.4 | Realization of investments: Construction of sedimentation-biofiltration system and its exploitation |
I/2012 – IV/2012 |
| A2.5 | Realization of investments: Ecohydrological adaptation of upper „Arturówek” reservoir |
I/2012 – IV/2013 |
| A2.6 | Realization of investments: Location and construction of buffer zones and floating mats of plants, and their exploitation |
I/2012 – IV/2012 |
| A2.7 | Realization of investments: Removal of the bottom sediments and undertaking additional activities limiting internal charge |
IV/2011 – II/2012 |